RIO DE JANEIRO (Reuters) - The serial delays in building Brazil's 12 World Cup stadiums should serve as a lesson to Russia and Qatar, the countries hosting the 2018 and 2022 tournaments, FIFA secretary general Jerome Valcke said on Thursday.

"We are late, we face difficulties and risks right up to the last minute because we haven't tested the installations, we need time to test them," Valcke told reporters in Rio after meeting with members of the Brazilian government and Local Organizing Committee.

"It's a lesson and definitely we will act differently and we will have to find a different way of working in Russia in 2018," Valcke said.

Brazil will host the World Cup in June and July but it faces a mad rush to get everything ready in time.

Three of the 12 stadiums are still not complete, including the Arena Corinthians in Sao Paulo that is due to host the opening match between Brazil and Croatia on June 12.

That arena and some others have yet to install the telecoms networks that will be used for broadcasters and media.

Originally, organizers said those networks had to be in place 90 days before the competition began in order to properly test them but with 77 days to go before the first ball is kicked work has not yet started.

"This is the last big challenge for the World Cup," Deputy Sports Minister Luis Fernandes told Reuters.

"After that the challenges are operational, in other words, holding the test events to see if we can make things better."   Continued...

 
FIFA Secretary General Jerome Valcke talks during a news conference at the Maracana stadium in Rio de Janeiro March 27, 2014. REUTERS/Ricardo Moraes