BRIEF-Thompson Creek Metals Co Q1 daily mill throughput at Mount Milligan averaged 58,099 tonnes

Tue Apr 12, 2016 5:16pm EDT
 
Email This Article |
Share This Article
  • Facebook
  • LinkedIn
  • Twitter
| Print This Article
[-] Text [+]

April 12 (Reuters) - Thompson Creek Metals Company Inc :

* During Q1 of 2016, daily mill throughput at Mount Milligan averaged 58,099 tonnes, compared to 39,569 tonnes

* Total concentrate production for Mount Milligan for three months ended March 31, 2016 was 40.1 thousand dry tonnes Source text for Eikon: Further company coverage: (Bengaluru Newsroom: +1-646-223-8780)