BRIEF-TMAC sees Hope Bay project stockpile by Dec 31 at 110,700 tonnes of ore

Aug 11 (Reuters) - TMAC Resources Inc

* Use about $23 million of net proceeds from bought deal financing in 2016,with balance of $33.5 million to be spent in 2017 for Hope Bay project

* TMAC continues on track and on budget 18 months into 24 month plan for hope bay’s path to production

* “as of this week,we are approximately 87 pct complete with steel erection,wall panelling, roofing of mill building”

* Says “as of this week we are 75 pct complete on floor and plinth concrete pouring” for Hope Bay project

* Sees Hope Bay project stockpile by Dec 31 2016 at 110,700 tonnes of ore, with an estimated 55,600 ounces of contained gold Source text for Eikon: Further company coverage:

0 : 0
  • narrow-browser-and-phone
  • medium-browser-and-portrait-tablet
  • landscape-tablet
  • medium-wide-browser
  • wide-browser-and-larger
  • medium-browser-and-landscape-tablet
  • medium-wide-browser-and-larger
  • above-phone
  • portrait-tablet-and-above
  • above-portrait-tablet
  • landscape-tablet-and-above
  • landscape-tablet-and-medium-wide-browser
  • portrait-tablet-and-below
  • landscape-tablet-and-below