TransCanada says Gulf Coast pipeline project sticks to schedule

Tue Jan 22, 2013 3:47pm EST
 
Email This Article |
Share This Article
  • Facebook
  • LinkedIn
  • Twitter
| Print This Article
[-] Text [+]

CALGARY, Alberta Jan 22 (Reuters) - TransCanada Corp Chief Executive Russ Girling said on Tuesday that the company's $2.3 billion Gulf Coast project is on schedule and he expects 700,000 barrel-per-day pipeline to open by year end.

Speaking to reporters in Calgary, Girling said work on the project is 40 percent complete and welding on the 485-mile (780-kilometer) pipeline should be completed by the end of September. The Cushing, Oklahoma, to Nederland, Texas, pipeline - the southern leg of the controversial Keystone XL project - will be then be filled with oil and tested in the fourth quarter.

"It's not going to be a matter of weeks but the end of the year is the best that we can do," he said.