SAO PAULO Dec 4 (Reuters) - Brazil's Copersucar expects a raw sugar warehouse at its fire-damaged terminal in Santos to resume shipping in January and additional export capacity to be available around May, the company said in a newspaper interview published on Wednesday.

The Oct. 18 fire had taken most of the 10-million-tonne-per-year Santos sugar terminal offline.

Chief Executive Officer Luis Roberto Pogetti told the Valor Economico daily that Copersucar, the world's largest sugar and ethanol trader, had managed to contract sufficient export capacity in Brazil from other traders to guarantee all shipments.

Pogetti said the 47-odd associate mills that hold most of Copersucar's equity would probably approve the 100 million real ($42 million) capital expansion in a meeting planned for Dec. 17. The funds will help shore up capital for the company as it rebuilds its terminal.

Global sugar prices spiked after news of the fire at the world's largest sugar terminal, which had just finished doubling its capacity in June, raised concerns over the loss of Brazil's ability to export.

But the fire left the terminal's shiploading and railway offloading equipment undamaged. The bagged, white sugar warehouse was also left largely intact, and one of five raw sugar warehouses was less damaged than the others.

Pogetti said he expected exports from this less-damaged warehouse, which can move 250,000 tonnes of raw sugar a month, to resume in January.

Then in May, the facility will go offline temporarily while it is linked up with two other raw sugar warehouses that are expected to come back on line then. This would return the terminal's capacity to 4 million tonnes a year, Pogetti said.

That is still less than half the total capacity before the fire but enough to allow Copersucar to meet all delivery commitments, Pogetti said. The company does not expect the terminal to return to full capacity until early 2015.   Continued...