(Corrects headline and text throughout to make clear that the figures are based on pre-feasiblity and feasibility studies and that the company has not made final decisions on construction)

Feb 22 (Reuters) - Barrick Gold Corp , the world's largest gold miner, estimated spending of about $2 billion if it decides to proceed with projects in Nevada and Peru.

Barrick, releasing updated pre-feasibility and feasibility studies on the projects, also said on Monday it would redeem up to $750 million of notes to help cut debt by at least $2 billion this year.

The company's U.S.-listed shares were down about 3 percent at $12.18 in premarket trading on Monday.

Barrick said a pre-feasibility study estimated $1 billion in initial capital spending on its Goldrush project in Nevada, based on a start of construction in 2020.

The project would produce 440,000 ounces of gold a year, with all-in sustaining costs of $665 per ounce.

Another pre-feasibility study estimated that $640 million would be needed to extend the life of the Lagunas Norte project in Peru by about nine years.

The Toronto-based miner said a feasibility study showed $300 million to $325 million would be required to boost production at its Turquoise Ridge mine in Nevada.

The proposed Cortez project in the state, which is in the pre-feasibilty stage, would require an estimated $153 million, with a construction start in 2019-2020.   Continued...