Buzzard field hit by North Sea pipeline outage

Fri Apr 25, 2008 5:38pm EDT
 
Email This Article |
Share This Article
  • Facebook
  • LinkedIn
  • Twitter
| Print This Article | Single Page
[-] Text [+]

By Jeffrey Jones

CALGARY, Alberta (Reuters) - The 200,000 barrel a day Buzzard oil field in the North Sea is among dozens that must stop pumping as a key pipeline powers down due to a strike planned this weekend at a Scottish refinery, Nexen Inc NXY.TO, the field's operator, said on Friday.

"As they go through those procedures, then we'll get notice to do similar things. It just kind of piggybacks off that," Nexen spokesman Mike Harris said. "Then we wait until they tell us we can bring it back up again."

BP Plc (BP.L: Quote), which runs the Forties pipeline that supplies about half of Britain's crude, started shutdown procedures on Friday. The Grangemouth refinery, about 34 km (21 miles) northwest of Edinburgh and the target of the labor dispute, supplies electricity to the pipeline.

The situation was a factor in a jump of more than $2 in world oil prices on Friday to $118.52 a barrel.

Nexen is one of numerous Canadian energy companies with operations in the North Sea. Others with production affected by shutdown of the 700,000 bpd pipeline include Talisman Energy Inc TLM.TO, Canadian Natural Resources Ltd (CNQ.TO: Quote) and Oilexco Inc OIL.TO

The Forties pipeline system ships crude from about 70 oil fields. The strike at the Ineos-operated refinery, due to start Sunday, has raised fears of fuel shortages in Scotland and northern England.

Harris said it will take time for the Buzzard platform to return to normal rates when the pipeline starts running again.

"You don't flip it on and get straight to big rates again. It probably takes up to two days to ramp up to where we were before," he said.   Continued...